Boomers Bar

The A's Ballpark Is Rising on the Strip, and Vegas Baseball Season Has Already Started

Steel is going up, roof trusses are landing, and the A's already played a real homestand in town this year. Here's where the Strip's future ballpark stands and why Boomers is the easiest place to keep tabs on it.

Boomers Bar · July 24, 2026 · 6 min read

Key takeaways

  • As of the most recent construction updates, crews had the concourse roughly 50 to 60 percent poured up to the third level, with 300 to 400 workers on site daily.
  • Steel framing for the upper seating levels is largely wrapped up and the first roof truss arches are already in place, with the project still tracking toward an early 2028 opening.
  • Vegas got an actual preview of big-league baseball this June, when the A's played a real regular-season homestand against the Brewers and Rockies at the current Las Vegas Ballpark.
  • Ticket pricing for the new Strip stadium is expected to run $20 to $30 at the low end, and local sports bars are already becoming the default gathering spot for fans who can't wait until 2028.
DIAMOND RISING
The Strip Ballpark, By the Numbers
50-60%
Concourse concrete poured as of the latest construction update
33,000
Planned seating capacity for the domed ballpark
6
Regular-season A's games already played in Las Vegas this June
$20-$30
Target low-end ticket price range once the Strip stadium opens

Figures per construction trade officials, Athletics team leadership, and Las Vegas sports reporting, as of mid-2026.

You Can Actually Watch This One Grow

Drive down the Strip these days and it's getting harder to ignore that half-moon shape climbing into the skyline. The Athletics' domed ballpark is a genuine construction site now, not just renderings and groundbreaking photos, and the milestones keep landing every few weeks. Crews have poured somewhere around half to two-thirds of the concourse up through the third level, according to trade union officials tracking the job, with a rotating crew of a few hundred workers moving through the site daily.

The steel framing for the upper seating bowl is essentially done wrapping the full seating area, a stretch of work that reportedly took about three months. From there the job moves overhead. The first roof truss arch went in a couple weeks before the most recent update, and a second arch installation kicked off in early July, the start of what's going to be the trickiest phase since the dome has to account for nets and structural quirks a typical open-air stadium doesn't.

Team president Marc Badain has kept saying the project is on budget and on schedule, with some parts actually running ahead. The target hasn't moved: an opening tied to the 2028 season, on a stretch of land that used to be a Strip parking lot and is now genuinely part of the skyline.

Vegas Already Got a Real Taste of This

Here's the part a lot of folks missed because it happened while everyone was focused on summer travel plans. Back in June, the A's played an actual regular-season homestand right here in Las Vegas, a three-game set against Milwaukee followed by another three against Colorado, all at the current Las Vegas Ballpark out by the Aviators' home. That's six real, count-in-the-standings games, the club's first regular-season action in this city ever, and a clear signal of what home games are going to feel like once the Strip stadium opens.

Ticket access rolled out in tiers, Aviators season-ticket holders first, then fans already on the A's 2028 priority list, then whatever was left to the general public. It's a small preview of how the eventual season-ticket rollout is probably going to work too, so if you've been thinking about getting in line early, that homestand was a decent hint at the pecking order.

Why This Is a Bar Story, Not Just a Construction Story

A new major league team landing in a city doesn't just change real estate, it changes what people do on a random Tuesday night. Sports bars nationally have been leaning harder into that shift already, expanding beyond the usual football-Sunday model into something built around whatever fandom walks in the door. Even the women's sports bar boom, which went from a handful of dedicated spots nationally to something like two dozen inside a year, is part of the same trend: people want a room built around the team they actually care about.

Vegas is about to get its own version of that with baseball. Until the dome is finished, the games are happening in Sacramento and, occasionally, right here at the current ballpark. Either way, the easiest way to catch first pitch on a weeknight without fighting Strip traffic is still a stool at a neighborhood spot with the right game on the right screen.

That's basically the pitch here at Boomers. We're not waiting until 2028 to start treating this like our team. Come catch the road games, argue about the roster, and let us know if you were one of the folks who scored tickets to that June homestand.

What's Left Before First Pitch on the Strip

The dome's roof is the next big hurdle, and it's genuinely a harder build than most people realize. Construction crews have compared the timeline favorably to Atlanta's Mercedes-Benz Stadium, which took about 39 months roof and all, while this project is targeting something closer to 30 to 32 months for the equivalent phase. One union official overseeing the job put it plainly: "we've never missed the deadline," which is either a great sign or a fun thing to bring up if the date ever slips.

Once it's done, the building holds roughly 33,000 fans under a glass curtain wall that's supposed to keep Strip views in play even with a roof overhead, using notably less concrete than Allegiant Stadium's structure despite sitting on a smaller footprint. Badain has also been consistent that pricing at the low end should land in the $20 to $30 range, aimed squarely at making sure a family night at the ballpark doesn't require a Strip-show budget.

5 Reasons This Ballpark Story Is Already a Bar Story

You don't need first pitch at the new stadium to start caring about this one. Here's why it's already changing how Vegas watches baseball.

  1. The homestand already happened: Six real regular-season games against Milwaukee and Colorado gave locals an actual preview instead of just a promise.
  2. The skyline already changed: The half-moon steel frame is visible from the Strip now, not just in renderings.
  3. Family-friendly pricing is the plan: Low-end tickets aimed at $20 to $30 keep the door open for casual fans, not just premium-seat regulars.
  4. Sports bar culture is already shifting nationally: New-team energy tends to reshape which bars become the go-to for a given fanbase, and Vegas is no exception.
  5. The road games count now: Until 2028, Sacramento home games and the occasional Vegas homestand are must-watch TV for the local fanbase forming early.
  6. Every update moves the date closer: Roof trusses, steel framing, and concourse pours are all visible progress toward an early 2028 opening.

Frequently Asked Questions

When is the new A's ballpark on the Las Vegas Strip expected to open?

Team officials are targeting an opening tied to the 2028 season, and recent construction updates say the project remains on schedule.

Did the Athletics already play games in Las Vegas?

Yes. In June 2026 the A's played a six-game regular-season homestand at the current Las Vegas Ballpark, three games against Milwaukee and three against Colorado.

How big will the new ballpark be?

Plans call for roughly 33,000 seats under a domed, glass-walled structure designed to keep Strip views in play.

Where can I watch A's games in Las Vegas until the new stadium opens?

Local sports bars, including Boomers, are the easiest spot to catch road games on the big screen while the Strip ballpark is under construction.